CR: Traffic and Power Block Between Diva and Kalyan on 18th and 19th October

Central Railway will operate special traffic and power blocks for infrastructure work for dismantling of FOB at Kalyan end of Dombivli station using road crane as under:

On 18/19.10.2019 (Friday-Saturday Night)

Diva-Kalyan Up and Dn fast lines from 01.10 hrs to 03.40 hrs

Dombivli-Kalyan 5th and 6th lines from 01.10  hrs to 05.00 hrs

On 19/20.10.2019 (Saturday-Sunday Night)

Diva-Kalyan Up slow line from 01.00 hrs to 03.30 hrs

Diva-Kalyan Dn slow line from 01.00 hrs to 05.00 hrs

Due to this infrastructure work, the train running pattern will be as under:

Suburban services:

Dn Slow services leaving Diva at 00.39 hrs, 00.53 hrs, 01.02 hrs, 01.13 hrs, 01.23 hrs and 01.33 hrs will be diverted on Dn fast line between Diva and Kalyan and will not halt at Kopar and Thakurli stations on 19 and 20.10.2019. Dn mail/express trains will be running behind schedule by 15-20 minutes.

Long Distance services:

Up mail/express trains arriving Mumbai area during the block period will be diverted via Kalyan and Diva and will arrive at their respective terminus15-20 minutes behind schedule. Dn mail/express trains leaving Mumbai area during the block period will be diverted on Dn slow line between Diva and Kalyan stations and will be running 15-20 minutes behind schedule.

Passengers are requested to bear with the railway administration for the inconvenience caused due to this block. 