Indian Railways (IR) is likely to complete 56 rail projects by the end of FY22 ( March 2022) according to the Railway Board. All these projects are under various stages of completion.
The projects are as follows:-
| S.No. | Name of Project | Length of Project (Km) | Month/Year of commissioning |
| 1 | Hansdiha-Godda New Line | 32 | Feb-21 |
| 2 | Omalur-Metturdam Patch Doubling | 29 | Feb-21 |
| 3 | Netravati-Mangalore | 2 | Feb. 21 |
| 4 | Nirmali – Saraigarh New line including Kosi Bridge | 22 | Mar-21 |
| 5 | Ahmedabad-Botad | 170 | Mar-21 |
| 6 | Pilibhit-Shahjahanpur Gauge Conversion | 83 | Mar-21 |
| 7 | Utretia – Raebarelli | 66 | Mar-21 |
| 8 | Ghazipur-Aunrihar | 40 | Mar-21 |
| 9 | Bhusawal-Jalgaon 3rd line | 24 | Mar-21 |
| 10 | Ambari-Falkata doubling | 38 | Mar-21 |
| 11 | Ambalapuzha-Haripad | 18 | Mar-21 |
| 12 | Tambram-Chengalpattu Gauge Conversion | 30 | Mar-21 |
| 13 | Ajmer-Bangurgram Doubling | 47 | Mar-21 |
| 14 | New Mynaguri-Gumanihat | 52 | Apr-21 |
| 15 | Jayanagar – Bijalpura | 52 | May-21 |
| 16 | Dhasa – Jetalsar GC | 104 | May-21 |
| 17 | Bangurgram-Guriya Patch DL | 47 | May-21 |
| 18 | Hajipur-Bachwara doubling | 72 | May-21 |
| 19 | Kankanadi-Panambur | 19 | May-21 |
| 20 | Raibarelli-Amethi doubling | 60 | May-21 |
| 21 | Pendra Road-Anuppur – 3rd line | 50 | May-21 |
| 22 | Daund-Gulburga doubling | 225 | Jun-21 |
| 23 | Khurda Rd-Bararng | 32 | Jun-21 |
| 24 | Katereah-Kursela patch doubling | 7 | Jun-21 |
| 25 | Bandel Boinchi 3rd line | 31 | Jun-21 |
| 26 | Mathura-Palwal 4th line | 80 | Jun-21 |
| 27 | Jallandhar-Pathankot-Jammu Tawi doubling | 209 | Jun-21 |
| 28 | Manoharpur-Bondamunda 3rd line | 30 | Jun-21 |
| 29 | Kharagpur-Narayanagarh 3rd line | 24 | Jun-21 |
| 30 | Arsikere-Tumkur doubling | 96 | June 21 |
| 31 | Raibareilly-Amethi Doubling | 60 | Jun-21 |
| 32 | Secunderabad-Mehboobnagar doubling | 85 | Jun-21 |
| 33 | Yelahanka-Penukonda doubling | 123 | Jun-21 |
| 34 | Bhadrachalam Road-Sattupalli | 54 | Jun-21 |
| 35 | Vijayawada-Gudiwada-Bhimavaram-Narsapur, Gudiwada-Machlipatnam | 221 | Jul-21 |
| 36 | Madurai – Bodinayakkanaur gauge Conversion | 90 | Sep-21 |
| 37 | Ahmedabad-Mehsana Gauge conversion | 69 | Oct. 21 |
| 38 | Digaru-Hojai doubling | 102 | Oct. 21 |
| 39 | Dausa-Gangapur City New Line | 93 | Nov. 21 |
| 40 | Sambalpur-Talcher doubling | 168 | Dec-21 |
| 41 | Sambalpur-Titlagarh doubling | 106 | Dec-21 |
| 42 | Raipur-Titlagarh | 203 | Dec-21 |
| 43 | Banspani-Daitari-Tomka-Jakhapura doubling | 164 | Dec-21 |
| 44 | Dankuni-Chandanpur 4th line | 25 | Dec-21 |
| 45 | Boinchi Shaktigarh 3rd line | 26 | Dec-21 |
| 46 | Bhimsen-Jhansi doubling | 206 | Dec-21 |
| 47 | Kurruppanthara-Chingavanam doubling | 27 | Dec. 21 |
| 48 | Bina-Kota doubling | 283 | Dec. 21 |
| 49 | Viramgam-Samakhyali doubling | 182 | Dec. 21 |
| 50 | Ayodhya- Varanasi – Railway Electrification | 188 | 28-Feb-22 |
| 51 | Guwahati-Lumding- – Railway Electrification | 180 | 28-Feb-22 |
| 52 | Mansi-Saharsa, incl. Saharsa-DauramMadhepura-Purnia& MM Banmakhi- Bihariganj Gauge Conversion | 169 | 31-Mar-22 |
| 53 | Palanpur-Makarpura section (WDFC) | 308 | 31-Mar-22 |
| 54 | Rewari-Dadri section (WDFC) | 127 | 31-Mar-22 |
| 55 | Palanpur -Kandla port-Mundra port-Bhuj- Railway Electrification | 475 | 31-Mar-22 |
| 56 | Hospet-Hubli-Vasco – Railway Electrification | 341 | 31-Mar-22 |