Adarsh Station scheme : 104 stations remaining

A total of 104 stations are remaining to be developed under the ‘Adarsh’ Station Scheme according to Railway Minister Piyush Goyal . This would be completed by the end of this fiscal he added.

Adarsh stations have various passenger amenities such as improved station building façade , retiring room, waiting room (with bathing facilities), separate waiting room for ladies, landscaping of circulating area, earmarked parking, signages, pay and use toilets, foot-over-bridge besides ramps at entry to station.The works are funded under the budget head ‘Passenger Amenities’.

The list of stations remaining to be developed zone- wise are as under:

Zonal Railways Indentified Developed (up to Oct 2019) To be developed
Central Railway 72 69 3
Eastern Railway 278 276 2
East Central Railway 58 48 10
East Coast Railway 52 39 13
Northern Railway 124 105 19
North Central Railway 42 35 7
North Eastern Railway 53 43 10
Northeast Frontier Railway 91 90 1
North Western Railway 41 36 5
Southern Railway 128 113 15
South Central Railway 68 68 0
South Eastern Railway 86 86 0
South East Central Railway 28 25 3
South Western Railway 45 36 9
Western Railway 62 59 3
West Central Railway 25 21 4
Total 1253 1149 104

The details of funds allocated since FY17 until the current fiscal FY20 are as under:

YEARS ALLOCATION in Rs crore
FY17 917.91
FY18 1470.79
FY19 2410.71
FY20 to date 3422.57

On board services

IR provides ‘Coach Mitra’ services in about 1050 train pairs . It is a single window interface to register coach related requirements such as cleaning, disinfestation, linen, train lighting, air conditioning and watering of coaches.

IR also provides on-board housekeeping services in nearly 1090
pairs of trains including Rajdhani, Shatabdi and other important long distance trains.Services include cleaning of coach toilets, doorways, aisles and passenger compartments on the run.