Centre’s nod to 3 multi-tracking projects in SECR ECR and SER

The Union Cabinet chaired by Prime Minister Narendra Modi on Tuesday cleared the construction of three multitracking projects in three railways zones- South East Central Railway (SECR), South Eastern Railway (SER) and East Central Railway (ECR).

The projects are as follows:

Gondia – Jabalpur doubling (SECR) 

Punarakh – Kiul 3rd and 4th line (ECR) [This is a part of the 400-km, multitracking of DDU -Jhajha section situated in Danapur division of ECR]

Gamharia – Chandil 3rd and 4th line (SER)

The total cost of these projects is approximately  Rs 9072 crore with completion likely by 2030-31. Once completed, it will add 307 km to the Indian Railways’ (IR) network,

 These projects will cover eight districts across the states of Maharashtra, Madhya Pradesh, Bihar and Jharkhand connecting 5,407 villages, with a population of about 98 lakh. The increased line capacity will significantly improve IR’s operational efficiency.

History of these 3 sections

Section todaySection constructed as Railway CompanyDistance in milesDate opened onGauge
Chandil -GamhariaPurulia -ChakradharpurBengal Nagpur Railway71.54January 22,18905’6″ BG
Chandil-GamhariaKandrra-Gomharria chordBengal Nagpur Railway6.42December 2,19195’6″ BG
Gondia -JabalpurJubbulpore-HowbaghBengal Nagpur Railway1.38September 15,19052’6″ NG
Gondia -JabalpurHowbagh-BurgiBengal Nagpur Railway16.1April7,19052’6″ NG
Gondia -JabalpurBurgi-NainpurBengal Nagpur Railway51.47July 5,19042’6″ NG
Gondia -JabalpurNainpur-GondiaBengal Nagpur Railway72.66April 18,19032’6″ NG
Punarakh-KiulLuckeeserai-DinaporeEast Indian Railway82.42November 17,18625’6″ BG
Punarakh -KiulJamalpur-KiulEast Indian Railway28November 7,18625’6″ BG

 These multi-tracking proposals decongest these saturated routes and streamline train operations. These routes  are essential for transportation of commodities-coal, steel, iron ore, cement, ballast and stone chips, fly ash, fertilizers, limestone, manganese, dolomite, food grains and POL. The capacity augmentation works will result in additional freight traffic of 52 MTPA(Million tonnes per annum).

 Better connectivity to tourist destinations

Destinations such as Kachnar Shiv Temple (Jabalpur), Kanha National Park(Balaghat), Gangulpara Dam and Waterfall, Pench National Park, Dhuandhar waterfall, Bargi Dam, Gomji-Somji temple, Chandil Dam, Dalma Hill Top, Hesakocha Waterfall, Raijama Ghati, DalmaWildlife Sanctuary, will be connected better than before.

Project details

RouteGondia Jabalpur DoublingPunarakh Kiul 3rd and 4th lineGamharia-Chandil 3rd and 4th line
Railway Zone /DivisionSECR /Nagpur excluding JabalpurECR /DanapurSER /Chakradharpur excluding Chandil
Route length in km2315026
Track length in Km25811568
Estimated cost in Rs crore523622681168
Project duration in years533
DistrictsGondia, Jabalpur, Balaghat, Seoni and MandlaPatna and LakhisaraiSaraikela Kharsawan
Important bridges1140
Major bridges651813
Minor bridges3696259
Rail over rail bridge002
Road Over bridge002
Road under bridge88013
Level crossings2844
Additional annual freight in mn tons7.61826.8
Logistics cost savings /yr in Rs crore350178139
Employment generation in lakh human days783418

Benefits

Gondia-Jabalpur doubling will provide an alternate shorter route from Varanasi / Prayagraj to Chennai /Bengaluru / Hyderabad. This project will serve power plants, ordnance factory and mines. A provision of Rs 450 crore for wildlife underpass and fencing has been made in this project.

Punarakh -Kiul 3rd and 4th line will improve connectivity of Northeastern and Eastern states with North India. This project will cater to mines, NTPC power plants (Barh, Barauni and Kanti) besides the cement industry in Daniyawan and Warsaliganj.

Gamharia Chandil 3rd and 4th line will cater to mines, power plants, industries and SEZs. It will increase transportation of coal and iron ore to various steel plants at Bokaro,Durgapur and Burnpur.