WR Rail Budget Allocations: 550 Cr for Mumbai Transport Projects, 279 Cr for Passenger Amenities

Western Railway gets 550 crores for Mumbai Suburban transport projects as well as over 270 crores for passenger amenities in the zone Read more »

CR Rail Budget Allocations: New Line and Doubling Projects Get 7,500+ Crores

Central Railway gets net plan outlay of Rs. 4,399 crores for FY21, over Rs. 7,500 crores for new line and capacity enhancement projects Read more »

Indian Railways Capex at All-Time High of 1.61 Lakh Crores for FY 2020-21

Indian Railways is set to invest in capital expenditure at an all time high of 1.61 lakh crores in FY 2020-21 for capacity enhancement and other infrastructure Read more »

SER: Work on Commissioning of 3rd Line – Several Trains Regulated

In view of 10 days Pre Non-Interlocking work from 12.12.19 to 21.12.19 and 2 days Non-Interlocking work on 22.12.19 and 23.12.19 at Bamra Yard in connection with commissioning of 3rd line work... Read more »

SECR: Target to Complete 493 km of Gauge Conversion, 2/3/4th Line in 2019-20

South East Central Railway (SECR) has been set a target to complete 493 km of works connected to Doubling, Tripling, Quadrupling or Gauge Conversion for the financial year 2019-20. Read more »

WR: Target of 559 km New Line, GC & Doubling in FY19-20, Includes 291 km from 18-19

WR has been set a target of 559 km of commissioning of New Line, Doubling and Gauge Conversion work in the financial year 2019-20, according to sources. Read more »

ECoR: Updated Timelines for 2018-19 Spillover New Line and Doubling Works

East Coast Railway recently submitted fresh timelines for completion of works that were to be completed within 2018-19 to the board. Read more »

ER: New Line, Doubling Works to be Commissioned in April, May 2019

Eastern Railway (ER) is likely to commission a slew of works over the next few months Read more »

CR: Several Doubling, Tripling Works to be Partly Commissioned in April, May, June

Several doubling/tripling works on Central Railway are likely to get partly commissioned in April, May and June 2019 Read more »

New Line, Doubling, Tripling and Gauge Conversion: Targets for FY 2019-20

In line with the plans and allocations set out for the previous and recent railway budgets, targets have recently been set out for various zones and executing organisations for the financial year... Read more »