CR Pune Division successfully commissions Ghorpuri–Hadapsar 3rd Line

Central Railway, Pune Division has successfully commissioned the Ghorpuri–Hadapsar 3rd Line on October 5,2026. This includes necessary alterations in Route Relay Interlocking, Pune and existing Electronic Interlocking, Hadapsar.

These works were carried out in a span of 15 days with the help of Track Relaying, Duomatic, Poclain, Hydra, JCBs and gas cutting equipment. A total manpower of 745 personnel including 485 contractual and 260 departmental staff were deployed for this work.

Benefits:

· Commissioning of the Ghorpuri–Hadapsar 3rd line will result in significant enhancement of section capacity of the Pune–Daund section and improve mobility of freight traffic, ensuring more efficient rake movement.

·It will provide a dedicated transfer line between the rake maintenance depot and the proposed Hadapsar Satellite Terminal without affecting UP/DOWN Main-line operations, thereby facilitating commencement of new train services from Hadapsar.

·The 3rd line will also serve as an alternate shunting neck for rake formation, sorting, engine/brake-van reversal and other shunting operations, thereby reducing detention on the Main line and improving punctuality, besides enhancing operational flexibility, facilitating smoother movement of both passenger and freight trains.

·Overall, it will help in decongestion of Pune station by facilitating transfer and operational activities through the Hadapsar Satellite Terminal.

The following works were executed as part of the project:

A summary of work carried out during the block
At PuneAt HadapsarShadow block
32 new/altered routes,Alteration carried out in the existing KYOSAN K5D make Electronic InterlockingReplacement of 140 Auto Tensioning devices
6 new/altered point machines28 new/altered routesReplacement of  insulated overlaps and section insulators
9 new/altered signals1 new/altered point machineReplacement of 900 metres of damaged contact wire restoring speed from 75 to 130 kmph,
11 new/altered tracks6 new/altered signalsErection of new portals and dismantling of rusted ones
24 new/altered ICC towards Hadapsar4 DC track circuitsProvision of AC brackets in turnout areas
  Work of Rail renewal, Tamping, Distressing, Greasing, Packing  & Welding also carried out