GC: Kelod – Bhimalgondi Section Commissioned, Itwari – Kelod Passenger Extended

The erstwhile Itwari - Kelod Passenger service has now been extended to Bhimalgondi, a newly completed station about 94 kilometres from Itwari Read more

SECR: Target to Complete 493 km of Gauge Conversion, 2/3/4th Line in 2019-20

South East Central Railway (SECR) has been set a target to complete 493 km of works connected to Doubling, Tripling, Quadrupling or Gauge Conversion for the financial year 2019-20. Read more

Itarsi – Budhni 3rd Line: CRS Inspection Today

The Commissioner of Railway Safety (CRS) is expected to inspect the newly completed 3rd line between Itarsi and Budhni on West Central Railway today. Read more

WR: Target of 559 km New Line, GC & Doubling in FY19-20, Includes 291 km from 18-19

WR has been set a target of 559 km of commissioning of New Line, Doubling and Gauge Conversion work in the financial year 2019-20, according to sources. Read more

ECoR: Updated Timelines for 2018-19 Spillover New Line and Doubling Works

East Coast Railway recently submitted fresh timelines for completion of works that were to be completed within 2018-19 to the board. Read more

SR: Fresh Timelines for New Line, Doubling, GC Originally Targetted for 2018-19

Southern Railway (SR) is likely to commission a slew of works in the second half of Financial Year 2020. These are works related to new line construction, gauge conversion and… Read more

ER: New Line, Doubling Works to be Commissioned in April, May 2019

Eastern Railway (ER) is likely to commission a slew of works over the next few months Read more

CR: Several Doubling, Tripling Works to be Partly Commissioned in April, May, June

Several doubling/tripling works on Central Railway are likely to get partly commissioned in April, May and June 2019 Read more

New Line, Doubling, Tripling and Gauge Conversion: Targets for FY 2019-20

In line with the plans and allocations set out for the previous and recent railway budgets, targets have recently been set out for various zones and executing organisations for the… Read more

Itarsi – Budhni 3rd Line Complete, Loco Trials Conducted

Line will help speed up dispatch from Itarsi. Read more