Indian Railways (IR) has identified several new projects for construction of new lines/doubling/gauge conversion and multi-tracking to its existing list in the budget document for 2026-27. The zone-wise list of such projects are as follows:

Central Railway (CR)

  • Rahuri–Shani Shignapur New Line (21.84 km)
  • Pachora–Jamner with extension upto Malkapur (narrow gauge to broad gauge conversion listed under New Lines) (84 km)
  • Miraj Chord line (1.73 Km)
  • Additional Hotgi Byepass line (5.85 Km)
  • Doubling between Puntamba-Sainagar Shirdi (16.50 km)
  • Multitracking of Panvel-Chouk section (17.28 km) Panvel Chord Lines between Panvel-Somtane and Panvel-Chikhli (7.54 Km)

East Coast Railway (ECoR)

(Note: These appear in the 2026-27 list but were missing from the 2025-26 excerpt, despite carrying a 2023-24 PB tag)

  • Mahanadi Coal Railway Limited Inner Corridor phase-I Doubling (10.93 km)
  • Flyover at Khurda Road for trains from Puri end to connect the DN grid at Khurda Road (17.41 km)
  • Flyover at Titlagarh (8.11 km)

East Central Railway (ECR)

(Note: These appear in the 2026-27 list but were missing from the 2025-26 excerpt, despite carrying a 2023-24 PB tag)

  • Ara bypass line – Jagjivan halt to existing Ara-Sasaram line through link cabin (3.06 km)
  • Multi tracking of Son Nagar-Andal (374.53 rkm)
  • Y-connection between Kuju – Ranchi Road station (7.27 km)
  • ROR at Sasaram connecting GC to Ara-Sasaram Line (8.95 Km)
  • Nawadah–Pawapuri New Line (25.10 km)

Eastern Railway (ER)

  • Murarai-Barharwa 3rd line (48.90 Km)
  • Dankuni-Baltikuri 3rd & 4th line (17.26 Km)
  • 3rd line between Ranaghat-Krishnanagar City (26 Km)
  • 4th line between Pakur & Gumani stations (18.48 Km)
  • Bhagalpur-Jamalpur 3rd line (53 Km)
  • Ranaghat – Bangaon doubling (32.93 Km)
  • Bhagalpur-Dumka-Rampurhat doubling (177 Km)

North Eastern Railway (NER)

  • Doubling between Katra & Ayodhya Dham stations (9.65 km)
  • 4th line between Burhwal-Gonda Kacheri (55.75 Km)

Northeast Frontier Railway (NFR)

  • Banarhat (India) to Samtse (Bhutan) (19.55 km)
  • Kokrajhar (India) to Gelephu (Bhutan) (69.05 km)
    Aluabari Road – Thakurganj Doubling (19.95 km)
  • Furkating-New Tinsukia Doubling (194 km)
  • Aluabari Road – New Jalpaiguri 3rd & 4th line (57 km)

Northern Railway (NR)

New rail line works across Indian Railways (Umbrella work 2026-27)

  • Chord Line between Alal-Himmatana (12.52 km)
  • Bypass line at Ayodhya (1.50 km)
  • Bypass / chord line at Ayodhya Cantt (between Salarpur-Masodha) (6 km)
  • Y-connection at Garhi Harsaru to avoid reversal at Garhi Harsaru (2.5 km)
  • 3rd line between Dilkusha- Malhaur (8.20 km)
  • Chord line between Bishanpura Haryana-Jind City (5.21 km)
  • 3rd line between Delhi Kishanganj- Shakurbasti (7.24 km)
Semaphore signals at Pokaran Picture Courtesy-Vivek Pillay

North Western Railway (NWR)

  • New line between Ramdevra and Pokhran via Bhairav Gufa–Kailash Tekri (13.38 km)
  • Churu Bypass Line (4.85 km)
  • Doubling between Lalgarh & Bikaner East Cabin (11.08 Km)
  • Doubling from Umra to Debari stations (24.78 Km)

South Central Railway (SCR)

  • Rail over rail at Pagdipalli (8.54 km) connecting Bibi Nagar and Bommaipalli stations
  • Doubling between Motumari – Vishnupuram (88.81 km) and Rail over Rail (RoR) at Motumari (10.877 Km)
  • Bypass line between Nashkal (Pindial) – Hasanparti Road (24.55 km)
  • 3rd line between Gudur-Renigunta stations (83.17 km)
  • Tirupati-Pakala-Katpadi Doubling (104.39 Km)
  • Aurangabad (Chhatrapati Sambhajinagar) – Parbhani Doubling (177 Km)

South East Central Railway (SECR)

  • Doubling between Urkura – Raipur Store Depot (3.0 KM)
  • Chord line between Ex-Gurda to Robertson to avoid Kharsia for loaded trains going towards Raigarh from CERL (6.42 KM)
  • 4th line between Sarona- Bhilai (17.30 km)
  • 4th line between Durg- Rajnandgaon (31.0 km)
  • 4th line between DLBS (Durg link block cabin)-Durg (3 km)
  • Gondia – Balharshah (Chanda Fort) Doubling (240 Km)
  • 4th Line between Dadhapara- Bilaspur (3.48 Km)
  • Dagori to Nipania 4th line (6.86 Km)
  • Gondia-Dongargarh 4th line
  • Rowghat–Jagdalpur (140 km)

South Eastern Railway (SER)

  • Bypass line with Rail flyover from Gundabihar end to Chandil (10.60 Km)
  • Adra-Sanka-Rukni doubling (13.60 Km)
  • Rail Flyover at Anara from Rukni to Anara station (10.63 Km)
  • Bimalgarh-Barsuan Doubling (21.13 Km)

Southern Railway (SR)

  • 3rd & 4th line between Attipattu- Gummidipundi (22.52 KM)
  • 5th & 6th lines between Perambur and Ambattur stations (6.4 Km)
  • 4th line between Tambaram-Chengalpattu (30.02 km)

South Western Railway (SWR)

  • Doubling of Ballary – Chikjajur (185 Km)

West Central Railway (WCR)

  • Rail over Rail flyover between Karhi-Kaima (4.975 Km UP & 6.785 km DN)
  • Chord line between Karhi- Sagma stations (5.31 Km)
  • Itarsi-Bina 4th line (237 Km)

Western Railway (WR)

  1. Ratlam-Nagda 3rd & 4th line project (41.38 Km)
  2. Vadodara-Ratlam 3rd & 4th line (259 Km)
  3. Doubling of Devbhumi Dwarka (Okha) – Kanalus (141 Km)
  4. New double line between Vadhavan Port and New Palghar station (22.23 km)
  5. Deshalpar–Hajipir–Luna and Vayor–Lakhpat New Line (145 km)