Indian Railways (IR) has taken up the following projects for implementation. For ease of reading , we at www.railpost.in have sub divided the long list into several parts . The list of projects under part -6 is as as follows:
Tindivanam-Nagari new line (184 km) at Rs 3,631 crore
Morappur-Dharmapuri new line (36 km) at Rs 359 crore
Nagapattinam-Tiruturaipundi new line (43 km) at Rs 742 crore
Trivandrum-Kanyakumari doubling (87 km) at Rs 3,785 crore
Arakkonam yard 3rd and 4th line (6 km) at Rs 98 crore
Perambur – Ambattur 5th and & 6th lines (6 km) at Rs 178 crore
Irugur-Podanur doubling (11 km) at Rs 277 crore
Tambaram-Chengalpattu 4th Line (30 km) at Rs 757 crore
Attipattu-Gummidipundi 3rd and 4th line (23 km) at Rs 375 crore
Tirupati-Pakala-Katpadi doubling (105 km) at Rs 1332 crore
Tindivanam-Gingee-Tiruvannamalai new line (71 km) at Rs 1400 crore
Atipattu – Puttur new line (88 km)at Rs 1700 crore
Chennai – Cuddalore via Mahabalipuram new line (179 km) at Rs 2670 crore
Junagarh-Nabarangpur new line (116 km) at Rs 2,865 crore
Nabarangpur-Jeypore new line (41 km) at Rs 748 crore
Jeypore-Malkangiri new line (130 km) at Rs 2,344 crore
Malkangiri – Pandurangapuram new line (174 km) at Rs 3,592 crore
Buramara-Chakulia new line (60 km) at Rs 1,459 crore
Gunupur-Therubali new line (74 km) at Rs 1,166 crore
Puri – Konark new line (32 km) at Rs 492 crore
Badampahar-Kendujhargarh new line (82 km) at Rs 1,876 crore
Bangriposi-Gorumahisani new line (86 km) at Rs 2,269 crore
Bargarh Road-Nawapara Road new line (138 km) at Rs 2,622 crore
Vizianagram-Titlagarh 3rd line (265 km) at Rs 6,996 crore
Jarapada- Budhapank 3rd and 4th line with flyover at Talcher (101 km) at Rs 810 crore
Budhapank- Salegaon via Rajatgarh 3rd and 4th line (170 km) at Rs 2,023 crore
Nergundi – Vizianagaram 3rd line (385 km) at Rs 4,963 crore
Kottavalasa-Koraput doubling (189 km) at Rs 2,500 crore
Koraput-Singapur Road doubling (165 km) at Rs 2,362 crore
Jagdalpur-Koraput doubling (107 km) at Rs 1,547 crore
Jharsuguda-Bilaspur 4th line (206 km) at Rs 2,596 crore
Bondamunda-Ranchi doubling (159 km) at Rs 3,029 crore
Narayangarh-Bhadrak 3rd line (153 km) at Rs 2,136 crore
Bhadrak-Nergundi 3rd Line (92 km) at Rs 1,284 crore
Nangal Dam- Daulatpur Chauk-Talwara-Mukerian (123 km) at Rs 2018 crore
Chandigarh-Baddi new line (33 km) at Rs 1540 crore
Baddi-Ghanauli new line (25 km) DPR prepared
Bhanupalli-Bilaspur-Beri new line (63km) at Rs 6753 crore
Bilaspur – Manali – Leh New line (489 km) -DPR prepared, anticipated cost is Rs 131000 crore as tunnel length is 270-km
Pathankot – Joginder Nagar gauge conversion (200 km) – DPR has been sanctioned
This information was provided by Union Railway Minister Ashwini Vaishnaw in the Rajya Sabha on March 13,2026.